LPG

Liquefied Petroleum Gas (LPG)

Fabrication options for our Liquefied Petroleum Gas (LPG) industry clients include:

  • Provision of cargo tank design and fabrication.
  • Onsite provision of post weld heat treatment (stress relieving) via Twin Brothers’ custom-designed furnace, which is the largest in the United States.

Project Experience

  • Cargo Tanks
    • Project type: Cargo tanks.
    • Scope of work: Fabrication of ASME VIII Div. 1 coded 1,400 ton tanks, heat treated in PWHT furnace and transport
  • Cargo Tanks for LPG Transportation Barge
    • Project type: Oil and gas marine transportation.
    • Location: U.S. inland and offshore waterways.
    • Scope of work: Fabrication of four cargo tanks each being 17 feet diameter by 203 feet in length. Each tank weighed 350 tons.
    • Challenges faced: Complex load out plan requiring multiple cranes.  
    • Delivery time: 12 months fabrication time.